As we welcome October, it’s astonishing to realize that we’ve journeyed through ten months of the 2023 construction season.I am grateful for the unwavering dedication and relentless effort each of you has poured into your work this year. Our industry’s challenges are undeniably demanding, but together, we’ve achieved remarkable success on every project we’ve undertaken.

As we approach the final stretch of 2023, I encourage all our field teams to continue prioritizing safety and delivering exceptional results. Let’s wrap up this year on a solid note, personally and as a united force within our company. Here’s to stepping into 2024 with unwavering confidence and continued success.

Mark Hoffman

Mark Hoffman

VP - Equipment

HOFFMAN PROJECT UPDATES

Eastbound and Westbound IH 94 Osseo, WI

Started 8/11/ 2022, completion 11/15/2024

Since 2022, notable progress has been made on the IH-94 roadway project, with a 3.5-mile temporary asphalt roadway already laid and eastbound lane reconstructions finishing. 2024 promises an enhanced commuting experience as westbound lanes are set to be rejuvenated, marking the project’s completion by Fall. Engaging a myriad of infrastructural enhancements like new concrete pavements, water management, and robust roadway infrastructure, the endeavor signifies a pivotal step towards safer and more efficient travel through IH-94. We value your continued patience and cooperation during these transformative times.

A photo of a road construction site built by Hoffman Construction Company
A photo of a road construction site built by Hoffman Construction Company
A photo of a road construction site built by Hoffman Construction Company

TUNNEL CITY PROJECT

Started 6/2023, completion 10/2023, approximate quantity of excavation 600,000 CY

Hoffman leadership team extends their gratitude to the dedicated HCC crew for their efforts in “pushing” (pun intended) this project to another year of SAFE production at Tunnel City sand mine!

A photo of the tunnel city project constructed by Hoffman Construction Company
A photo of the tunnel city project constructed by Hoffman Construction Company

HOFFMAN UPCOMING PROJECT

WisDOT has selected Hoffman Construction to Construct the Bracket Project Wisconsin IH 94 Westbound and Eastbound. This significant undertaking valued at $70 million is scheduled throughout three seasons, 2024-2026.

HOFFMAN TEAM GATHERINGS

HCC Crew Recognition

Hoffman Construction recently celebrated its team’s commitment to safety and dedication at an event attended by 85 individuals from the MLWK job sites, underscoring the company’s values and appreciation for its hardworking crew. President Chris Goss expressed deep gratitude for the team’s efforts, highlighting the company’s family-oriented values. CEO Jim Hoffman discussed the company’s journey from modest beginnings to industry prominence, attributing the success to persistent determination, resilience, and a steadfast commitment to excellence.

Photo of crew members from Hoffman Construction Company enjoying a recognition lunch held by Hoffman leader ship
Photo of crew members from Hoffman Construction Company enjoying a recognition lunch held by Hoffman leader ship
Photo of crew members from Hoffman Construction Company enjoying a recognition lunch held by Hoffman leader ship

SPECIAL ANNOUNCEMENT

Mason Stelter, one of Hoffman’s up and rising project managers, also serves in the Navy Reserves and is set to deploy this month with the Naval Mobile Construction Battalion (NMCB) 25 or better known as the Seabees.

The Seabees are a construction unit within the United States Navy with a rich history and a “Can Do!” motto. He will receive extensive job and area specific training in California prior to shipping out.

Mason will take this Navy training and the years of experience he has acquired at Hoffman Construction Co. to Kuwait and the surrounding countries of the Middle East. He will be involved in new construction & reconstruction of military and local infrastructure including roads, schools, water wells, etc.

The Glendale Project Team took a break from work to thank Mason for all he has done at Hoffman and send him off. Hoffman wishes him the best on his deployment and thanks him for his service to America.

–Keegan Flynn
A photo of a half make instruction employee who is set to deploy

Other News

Hoffman Construction was part of the WTBA Launch of: Work Zone Safe Wisconsin

Keeping Work Zones Safe: A New Approach to try and Cut Down on Distracted Drivers.New Wisconsin legislation requires 30 minutes of work zone safety driver's education for student drivers, and starting Tuesday, 4/23/24, students can fulfill that requirement online and for free. The campaign's ...

Hoffman Construction April Newsletter

APRIL 2024 NEWSLETTERHello Hoffman Team, As we head into another season, I want to give everyone some updates and praise for my staff. So often, we get so focused on building a job that everyone forgets about what goes on behind the scenes. The three most important tasks at Hoffman ...

Hoffman Construction March Newsletter

MARCH 2024 NEWSLETTERHello all! Spring is just around the corner. What a weird winter, if you can call it that. On January 31 of this year I was running some errands and got passed by a convertible with its top down. At the next intersection, I saw a guy on his Harley Davidson. Now that was a ...