September 2026
A project update from travis
Project Manager
To date, our teams have successfully managed:
- 3.5 million cubic yards of earthwork
- Nearly 1.0 million tons of aggregates
- 660,000 cubic yards of rock excavation
- 863,000 tons of on-site crushing
- 110,000 linear feet of storm, sanitary, and watermain piping
- 525 sanitary and storm sewer structures installed
Supporting Our Partners & Nearing the Finish Line
Hoffman crews have played a vital role in keeping the entire site moving, supporting eight separate trade partners by managing all on-site excavation and backfilling operations—from temporary electrical setups to telecom trenching.
Currently, our crews are busy finishing the curb, sidewalk, and paving work, as well as completing topsoil, shouldering, and supporting trade partners with site lighting and conduit installation. Additionally, infrastructure upgrades are nearing completion, including the CTH A turn lanes, bypass lane, and USH 151 off-ramp expansions.
Safety First: A Culture Second to None
Most importantly, our crews and trade partners have reached an incredible milestone: accumulating more than 2 million work hours and counting without an OSHA- recordable incident.
In civil construction, this is a monumental achievement that deserves to be celebrated by everyone on the project. It sets a phenomenal benchmark for all future work.
More than 200 Hoffman employees have lent their hands and expertise to deliver this unique and challenging project. Thank you to each of you—and to your families—for your hard work, relentless focus on SAFETY, dedication, and positive attitude. You have truly built a project culture that is second to none!
Montello, Church street sth 22
Wentworth-Brule USH 2
Welcome, K9 Kor!
Mental Health Resources
To make it easier, we’ve created a Linktree with important mental health resources and support numbers.
Years
Help Us Celebrate 100 Years of Hoffman!
Help Keep Our Crews Safe